On Monday the excavators returned to backfill and grade around the house. I am pleased with how the house sets on the property!
To allow for the septic line, the location for the geothermal loops needed to be adjusted slightly – after discussing this with the company that sets the loops, this will not be a problem.
The excavators returned on Tuesday and installed the water line from the road to the house. Our goal was to use 1-1/4″ tubing – but this was special order, so they upgraded to 1-1/2″ – it looks like a fire hose!
Wednesday was the first day where there was no real progress – I am sure that this will be the first of many.
On Thursday the first lumber order was delivered – but the framers were not ready to start. Tony indicated that they will be there bright and early on Friday – let’s hope!