August 2nd, 2009

Things are moving along quite nicely. We think the rough-in electrical should be done within a week. The air handling system rough in should be completed by this Tuesday.

We’re using an environmentally friendly composite material for the front porch decking as well as the two decks on the back of the house.  The gray color really compliments the siding color.

Decking

Speaking of siding… the guys ran out and had to order more. Probably another week or so until all the siding is complete.

We need it to stop raining for about a week or more – along with temperatures in the 90′s – so the ground can dry enough to install the septic system.