November 8th, 2009
 

Again, it has been a while since the last post – in addition to work on the house, Jyll and I were married in October.

As for the house, a lot has taken place… the electrical finish was complete (it is nice not to need extension cords to do everything), plumbing is complete (the port-a-pot went bye-bye and one porcelain pot was installed in the house), the underside of the back porch was completed, enough trim was added to get ready for the carpet installation, railing were installed and many other odds and ends.

On Friday we had the county final inspection – there are 3 minor items that need to be remedied before we can move in!

  1. Add a light fixture to illuminate the basement stairs and move the switch to the very bottom of the stairs
  2. Add porch railing on the deck off of the laundry room- because the ground settled, it is 31″ from the deck to grade and code requires a railing if it is greater then 30″. The railing at the master bedroom needed to be extended 2 feet so that no one would come around and take the 10 foot step down.
  3. Shorten the length of the overflow on one of the hot water heater.

The fixes are:

  1. Add a fixture and move the switch
  2. Add railing and steps across both the deck and the covered porch – DONE!
  3. Cut the tube – DONE!

I will add the light fixture this week and get everything wrapped up so that we can start moving in! We had not decided on what railing to add and had planned on waiting until spring to make some decisions, but it was easier to get it done.

More recent projects have included painting the top edge of the stair well (this was a feat after erecting a temporary wall on the stairs to support a walk plank), tiled the master bath and the full bath on the first floor, carpeted the two bonus rooms using 2 X 2 carpet tiles, putting polyurethane on all the doors and frames and a bunch of odds and ends.

It has been nice to complete some projects that have a large visual impact. More pictures to follow.

Up next: carpet in the bedrooms gets installed on Friday, the laminate floor is in the house and ready to be installed, tile the 2nd floor bath, grout all of the tiled areas, install door and window casings, install the closet bars/shelves (wire), the last garage door openers.

 
September 16th, 2009
 

It has been a while since my (john’s) last post – it is a decision to keep working or blog, and the work has been winning.

It is hard to believe that only 119 days ago the excavator started digging for the basement! Jyll has provided some recent updates, but I have been working on so many things it is hard to list, but the highlights include: porch railings, garage floor, septic, interior painting, preparing and installing vinyl flooring in the laundry room/ 1/2 bath/short hall on the first floor, installing luan in preparation for laminate, central vacuum, retaining wall, backer board to prepare for tiling.

Today was one of those highlight days – the cabinets were installed. There were a few small problems, but nothing that can not be overcome. The Amish made look great!

Next up: continue to install the luan, finish the electric installation, install the sinks and start the finish plumbing and install the siding on the underside of the back covered porch. In order to live in the house the final inspection is needed – this county does not issue a CO, but there are the same requirements. To get ready for this inspection I will need to install the handrails in the stairways, a railing for the balcony in addition to the other projects that are in progress.

As the amount of daylight is decreasing, the evenings seem to get longer working on something. As things get finished up, the house is starting to look like a home!

 
September 7th, 2009
 

John started painting on Wednesday, September 2 and it was all completed by today, September 7. I was able to help a couple of days, but he did most of the work. The color choices really look amazing! We changed our mind on the laundry room and painted it Golden Mushroom instead of Austrian Ice.

The septic system was installed and approved by the Board of Health. The garage doors were installed last week. The HVAC guys have some finish work to do by the end of next week.

Enjoy the pictures!


 
August 27th, 2009
 

Drywall

The taping and mudding began yesterday. All the windows in the house were left open overnight to help with the drying process. The team anticipates finishing either Friday or Saturday.

Flooring

We’ve chosen Congoleum’s AirStep Plus for the entryway from the garage up to the kitchen. This includes the 1/2 bathroom, laundry room, and utility closet. The Satin Cloud pattern is what we selected. For the other bathrooms, we’re leaning towards ceramic tile similar to the sample shown below.

tileSample

The foyer, great room, dining room and office will be laminated flooring. The bedrooms, stairs and upstairs hallway will be carpeted. (More on all of that later!)

Screened-In Back Porch

We’re installing a stained pine board siding on the ceiling. Last week we picked up a discontinued outdoor fan at Lowe’s for an incredible price!

« Previous EntriesNext Entries »